Securing Crane Counterweights

Discussion in 'Flatbed Trucking Forum' started by Antler24, Apr 23, 2017.

  1. Jumbo

    Jumbo Road Train Member

    3,669
    7,389
    Sep 4, 2009
    Appleton, Wisconsin
    0
    Depends on the crane. You could get the tray, tray weights, carbody weights, side weights. Counter weight comes in all shapes and sizes.
     
    Razororange, Ozdriver, cke and 2 others Thank this.
  2. Truckers Report Jobs

    Trucking Jobs in 30 seconds

    Every month 400 people find a job with the help of TruckersReport.

  3. Jumbo

    Jumbo Road Train Member

    3,669
    7,389
    Sep 4, 2009
    Appleton, Wisconsin
    0
    They almost always have securement points and the weight right on them. I cannot think of any that dont.
     
  4. Op did your dispatcher tell you what your weight was for this pickup?
     
  5. Diesel Dave

    Diesel Dave Last Few of the OUTLAWS

    8,714
    24,938
    Jan 20, 2010
    Hesperia, Ca.
    0
    I haul them all the time. And they usually throw part of the jib section of the crane on top of the counterweights out here in Cali. You can you either, straps or chains, if you use straps, use softeners. If the counterweights are all concrete, you can still use either but if you use chains, I recommend the metal corners or else the chain will dig into the concrete eventually.
    All in all, it's an easy load driver. Nothing to worry about. You should see what they put on me when I haul those tower cranes. The swirling ring, cab, counterjib double stack, inverted jib sections. But again, your load is a piece a cake.
     
    Lepton1 and Ozdriver Thank this.
  6. Ozdriver

    Ozdriver Heavy Load Member

    767
    1,390
    Oct 16, 2015
    Australia
    0
    IMG_0769.JPG
    Like this Mack Titan on the same job I was on. He had 60 tons of counterweights but at first glance you think it's a light load.
     
    Old Iron, Oxbow, tucker and 9 others Thank this.
  7. Antler24

    Antler24 Light Load Member

    98
    124
    Mar 1, 2017
    0
    Well the load got postponed until 8am tomorrow. Still haven't figured out what type or how many Counterweights it'll be. Dispatch thinks it's going to be 3, each about 6'x4' and about 18" tall. Laid flat on deck. They aren't sure though. I contacted the shipper and left a message but didn't hear back.
    I'll try and post a pic when there are loading.
     
    MJ1657, Chewy352, Razororange and 3 others Thank this.
  8. passingthru69

    passingthru69 Road Train Member

    Probably still tearing down the crane
    That's the reason for delay
     
    Oxbow, Diesel Dave, soloflyr and 4 others Thank this.
  9. Jumbo

    Jumbo Road Train Member

    3,669
    7,389
    Sep 4, 2009
    Appleton, Wisconsin
    0
    Seems odd that you are getting three.
     
    Oxbow, cke, MJ1657 and 3 others Thank this.
  10. passingthru69

    passingthru69 Road Train Member

    Just about bet 2 counter wghts and a boom section makes 3. Lol
     
    Oxbow, Razororange, cke and 3 others Thank this.
  11. Jumbo

    Jumbo Road Train Member

    3,669
    7,389
    Sep 4, 2009
    Appleton, Wisconsin
    0
    Let's see driver, we are going to put on two counterweights. We were going to put a boom section on but now you are getting the block, the ball, rigging box, the steps off the tracks, our water cooler, and two bags of recycled aluminum cans.
     